What is this?
Dailies Settings controls how the daily works for your company. You choose which steps the daily shows, and in what order. You also choose which exceptions Clue flags on a daily, and if the foreman must explain them.
You can set it for the whole company. You can also give a sub-organization or one project its own settings.
Who's this for?
- Admins and executives, who set up how the daily works for the company.
- Operations managers, who need a different daily for one sub-organization or one project.
- Foremen, who see the steps and the exceptions that their company chose.
How to use it
Step 1: Open Dailies Settings
Go to Operations > Dailies. Click the gear icon at the top right.
Step 2: Choose where the change applies
The box at the top shows Organization, which is your whole company. Click it to pick a sub-organization or a project that already has its own settings.
Step 3: Add a sub-organization or a project
Click Add Sub-Organization or Add Project. Pick one from the list. It starts with the same settings as the company. Change only what is different.
Step 4: Choose the daily steps
Under Daily Steps, turn a step on or off with its switch. Drag a step by its dots to move it. The daily shows the steps in this order. The Summary is always last.
Step 5: Set the exceptions
Under Exceptions, set each one to Off, Optional or Required. Type the limit next to it, for example the hours gap. Click the arrow at the end of a row to see its reasons and the asset categories it checks.
Step 6: Save and check the daily
Click Save. Open a daily that is not submitted. The top of each step shows its number, for example Step 2 of 6. The Daily Report panel on the right lists the steps in your order.
The full details
- Who can open it: People whose role can see the Dailies settings. Other people do not see the gear icon.
- Who can change it: People whose role can change the Dailies settings. Other people see the values but cannot change them.
- Which setting a daily uses: The project's own settings first. Then the sub-organization's, then the company's. Then Clue's default.
- The steps: Crew, Assets, Materials & Tools, Production and Plan Tomorrow. Project and shift is always step 1. The Summary is always last.
- At least one step: You cannot turn off the last step that is on.
- Steps that are off: They show below the steps that are on, and you cannot drag them. A step you turn on stays in its row. Drag it to move it.
- Plan Tomorrow as a step: The foreman sees it after the steps before it, before the Summary. It shows only on a daily that is not submitted yet. See Plan Tomorrow.
- Off: Clue does not check the exception.
- Optional: Clue flags the line. The foreman can explain it, and the daily submits either way.
- Required: Clue flags the line. The daily does not submit until the foreman explains it.
- Reasons: The reasons a foreman can pick are set for the whole company. Pick Organization in the box at the top to change them.
- Reset: On a sub-organization or a project, Reset takes a value back to the one it gets from above.
- Remove: Remove Project Settings or Remove Sub-Organization Settings deletes all its own values. It then uses the settings from above.
- Revert to Clue Default: Takes every company value back to Clue's default.
Tips
- Set the company first. Then add a project only when that job really works differently.
- Start an exception as Optional. Make it Required when the foremen know what it means.
- Put Plan Tomorrow last if dispatch needs the lineup for tomorrow from every daily.
- After you save, open one daily and check the step numbers before you tell the foremen.