Link timecard entries to work orders to track labor costs per repair. This connection enables accurate maintenance cost reporting and mechanic productivity analysis.
Adding Time from Work Order Detail
Step 1: Open a work order from MAINTENANCE → Work Orders.
Step 2: Navigate to the Labor/Time section.
Step 3: Click "Add Time" or "Log Hours".
Step 4: Enter:
Mechanic name
Hours worked
Date of work
Notes (optional)
Step 5: Save the time entry.
Linking Existing Timecards
If time was already logged in Timecards:
Open the timecard entry
Find the Work Order field
Search and select the appropriate work order
Save to link them
Viewing Labor on Work Orders
Once linked, the work order shows:
Total hours spent
Labor cost (if rates are configured)
Who worked on it
When work was performed
Benefits of Linking
Cost tracking - See true repair costs including labor