Equipment Charge Timeline

Rates
Reading Time:
4 min read

What is this?

The Equipment Charge tab shows a visual timeline of every piece of equipment, where it was, what it was doing, and how much it cost. Each day is a colored block: green for Working, orange for Standby, purple for In Yard, blue for In Transit. Click any block to see the rate breakdown.

How to use it

Step 1: Open Equipment Charge

Go to Rates > Equipment Charge. The timeline shows equipment grouped by project/location, with daily charge blocks across the date range.

Equipment Charge timeline showing color-coded daily charges grouped by Bull Run Plant, Centreville Plant, Culpeper Plant, Gainesville Shop with dollar amounts

Step 2: Change the time view

Switch between Daily, Weekly, Monthly, and Quarterly views. Use the date picker to select a specific range.

Date picker showing Week, Month, Year, Custom options with calendar

Step 3: View charge details

Hover over any colored block to see the charge breakdown: rate factor, rate code, daily rate amount, operating cost, and total.

Charge tooltip showing WORKING - Working status, Mar 4-5 2026, Centreville Plant, Rate HVY-02, Rate 280/day, Operating 560, Total 560

Step 4: Edit a charge

Click a charge block to edit it. Change the date range, project, rate per day, rate factor, or charge method (5-day, 6-day, 7-day, or one-off).

Edit Charge dialog with start date, end date, project, rate per day, rate factor (YARD - In Yard), and charge method (5-day)

Filtering and grouping

Use Filters to narrow by organization, project, crew, asset type, product class, geofence, or ownership (owned/rented/leased).

Filters panel with Affiliated Organization, Project, Crew, Asset Type, Product Class, Geofence, and Ownership options

Use Data Structure to control how the timeline is grouped: by Project and Asset, or add Sub-Organization, Asset Type, and Product Class levels.

Data Structure panel with Project, Asset, Sub Organization, Asset Type, Product Class grouping options

The full details

  • Works on: Web app
  • Charge methods: 5-day (weekdays), 6-day, 7-day (every day), one-off (single charge)
  • Rate factors on edit: Choose from Working, Idle on Site, Standby, In Transit, In Maintenance, In Yard
  • Totals column: Shows the sum for the visible date range per equipment and per project

Tips

  • Use the Monthly view for invoicing. It rolls up daily charges into monthly totals per project.
  • Filter by project to prepare a client invoice. See every piece of equipment charged to that job with daily detail.
  • Check the charge method. 5-day is standard for most contractors. 7-day applies when equipment runs weekends.